Bihar
,
Sultanganj
,
Bhagalpur
Published :
Sep 2016
|
Updated :
April 5, 2024
Sultanganj-Aguwani bridge construction in Bihar delayed amid land acquisition hurdle
Reported by
Rahul Kumar Gaurav
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
220
Households affected
1054
People affected
2016
Year started
80
Land area affected
220
Households affected
1054
People Affected
2016
Year started
80
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

Several villagers in Bihar protested against the land acquisition for the Sultanganj-Aguwani Ghat Bridge, being built at a cost of Rs 1,710 crore. The villagers demanded compensation at commercial rates instead of agricultural rates. Several landlords refused to accept the compensation being awarded by the government.

The land is being acquired for building 25 kilometre approach road on either sides of the bridge. A total of 17 mouzas in Aguwani and eight mouzas in Sultanganj had been earmarked for acquisition for the project. From Aguwani side, the bridge will be connected to NH 31, while from Sultanganj side, it will be connected to Munger Mirzachowki four-lane via ROB near Tilakpur. However, the protests, which started in 2016, led to a significant delay in the starting of the project.

In 2018, it was reported that the process had been expedited for the access road to the Aguwani bridge on the Ganges. In 2020, it was reported that the construction of the bridge and approach road would soon begin after 470 out of 1,054 landholders accepted the compensation for the land between Aguwani to Pasraha. However, noting the reservations of some farmers, officials estimated that the construction of the bridge and access road would not be complete before 2022.

It was again reported in February 2021 that after consistent delays, the construction would start within a week. But land owners continued to protest, demanding increased compensation and refusing the compensation offered by officials. Following which, the Land Acquisition Authority deposited the compensation amount with the competent authority (Lara Court).

In 2022, Land Acquisition Officer said that the compensation for land acquisition was provided to the farmers and added that the construction of the bridge would be completed by 2022. However, on 30 April 2022, about 200 metres of the super structure of the bridge collapsed. The work resumed but on 5 June 2023, the foundation and super structure between pillars 10 and 12 collapsed, leading to further delay.

In January 2024, a report by the Bhaskar stated that the four-lane bridge will now be built in a new design. The construction work on the four-land bridge began again in March 2024.

2
Fact Sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

Demand for more compensation than promised

Demand for compensation

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Private

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Residential area, Other environmental services

Whether the project was stalled due to land conflict

Yes

Source/Reference

A total of 17 mauzas of land in Aguwani and eight mauzas of land in Sultanganj was to be acquired for the construction of a high level bridge and approach road on Ganga river between Sultanganj Aguwani Ghat. The project was delayed initially due to land acquisition.

Total investment involved (in Crores):

1710

Type of investment:

Cost of Project

Year of Estimation

2024

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

National Highways Authority of India

PSUs Involved in the Conflict:

Bihar Rajya Pul Nirman Nigam Limited, Bihar State Bridge Construction Corporation Limited

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

SP Singla Construction Private Limited

Did LCW Approach Corporate Parties for Comments?

No

Communities/Local Organisations in the Conflict:

Farmers

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Rahul Kumar Gaurav
Show more work
Latest updates
Nagaon
Assam

Farmers in Assam resist land acquisition for solar plant, beaten by police

Surat
Gujarat

Surat farmers claim fertile land re-included in Gujarat's development plan without consent

Gadchiroli
Maharashtra

Villagers in Gadchiroli campaign to shut down Surjagarh iron ore mine

Biswanath
Assam

Encroachment, land dispute pose threat to newly designated Behali Wildlife Sanctuary in Assam

Krishnagiri
Tamil Nadu

Residents in Krishnagiri protest against takeover of land by SIPCOT

Lower Siang
Arunachal Pradesh

Tension in Arunachal's Lower Siang over Likabali-Durpai road project amid boundary disputes

Kanyakumari
Tamil Nadu

Tamil Nadu revives plan to construct Kanyakumari Port despite protests by fisherfolk

Koraput
Odisha

Bauxite mining at Mali Parbat in Koraput seeks to displace and disrupt local livelihoods

Fact sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

Demand for more compensation than promised

Demand for compensation

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Residential area, Other environmental services

Whether the project was stalled due to land conflict

Yes

Source/Reference

A total of 17 mauzas of land in Aguwani and eight mauzas of land in Sultanganj was to be acquired for the construction of a high level bridge and approach road on Ganga river between Sultanganj Aguwani Ghat. The project was delayed initially due to land acquisition.

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us