Land acquisition for National Highway 66 causes conflicts across Kerala coast
Reported by
Dr. K.H. Amitha Bachan
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
People affected
2010
Year started
3567
Land area affected
Households affected
People Affected
2010
Year started
3567
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban and Rural
Ended
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban and Rural
Ended
1
Summary

National Highway 66 (NH 66) runs parallel to the western Indian coast, following a route from Panvel, south of Mumbai, to Kanyakumari, in Tamil Nadu. NH 66 runs through Maharashtra, Goa, Karnataka, Kerala and Tamil Nadu. Within Kerala, the NH 66 replaced the NH-17 and much of the NH-47. The expansion of the NH 66 into a 6 lane NH is underway in several of the states, however in Kerala several land conflicts along the NH route have prevented further construction, or in part, halted construction.
The NH 66 expansion will only be for 4 lanes in Kerala as opposed to the 6 lanes in other neighbouring states. A total of 3,567ha of land needs to be acquired for widening 590 km of highway corridor from Kasaragod - Thiruvananthapuram. The Union Ministry of Road Transport and Highways (MoRTH) has agreed to route ₹26,000 crore through the National Highways Authority of India (NHAI). As of January 2019, 2,560 ha are still required in widening the Kasaragod - Thiruvananthapuram stretch of the NH 66 by 45 m.
The project was proposed to be finished in 2020 however problems in land acquisition have delayed the project by a year. Land acquisitions were temporarily halted when the NHAI removed all national highway projects in Kerala from the high priority-I list, this decision was subsequently revoked a few days later, June (2019).
There are several stretches of the NH 66 route with ongoing land conflicts. In the north, near Kozhikode, massive resistance came from the residents of Puthuppanam near Vadakara and Azhiyur in Mahe. In 2018, protests against the land acquisition survey, for the NH 66 development, turned violent in the Malappuram district. Clashes left 15 policemen including injured. In February 2019, the Revenue Department officials continued to plant alignment stones for the proposed widening of National Highway 66 amid protest by residents along the stretch of the highway between Edappally and Moothakunnam. Samyukta Samara Samiti has accused the administration of trying to bulldoze its way to acquiring land. No public hearing had been conducted nor had statutory clearances for the project been obtained, said Hashim Chennampilly of the Samara Samiti. This led to delay in land acquisition.
In September 2020, notification was issued under the National Highway Act of 1956 to acquire 54.46 ha of land belonging to 11 villages. Between September 2020 and November, the public hearing will be conducted in villages by the tahsildar. The compensation will be decided according to Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The work is scheduled to start in 2021.

2
Fact Sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

Other Demand/Contention of the Affected Community

Region Classification

Urban and Rural

Type of Land

Both

Non-Forest (Grazing Land)

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

26000

Type of investment:

Investment Expected

Year of Estimation

2018

Page Number In Investment Document:

Has the Conflict Ended?

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Union Ministry of Road Transport and Highways

PSUs Involved in the Conflict:

National Highway Authority of India (NHAI)

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Wilbur Smith Associates Inc. USA ; Guruvayur Infrastructure Pvt Ltd

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

local landowners, Fishing communities, Samyukta Samara Samiti

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Dr. K.H. Amitha Bachan
Show more work
Latest updates
Nagaon
Assam

Farmers in Assam resist land acquisition for solar plant, beaten by police

Surat
Gujarat

Surat farmers claim fertile land re-included in Gujarat's development plan without consent

Gadchiroli
Maharashtra

Villagers in Gadchiroli campaign to shut down Surjagarh iron ore mine

Biswanath
Assam

Encroachment, land dispute pose threat to newly designated Behali Wildlife Sanctuary in Assam

Krishnagiri
Tamil Nadu

Residents in Krishnagiri protest against takeover of land by SIPCOT

Lower Siang
Arunachal Pradesh

Tension in Arunachal's Lower Siang over Likabali-Durpai road project amid boundary disputes

Kanyakumari
Tamil Nadu

Tamil Nadu revives plan to construct Kanyakumari Port despite protests by fisherfolk

Koraput
Odisha

Bauxite mining at Mali Parbat in Koraput seeks to displace and disrupt local livelihoods

Fact sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference