Uttarakhand
Dehradun, Tehri Garhwal, Chamoli, Pauri Garhwal, Rudraprayag, Pithoragarh, Champaway
,
Gangotri
,
Uttarkashi
Published :
Mar 2023
|
Updated :
Char Dham highway development project continues in Uttarakhand despite opposition from different groups
Reported by
Chicu Iogariwar
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
People affected
2017
Year started
Land area affected
Households affected
People Affected
2017
Year started
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Infrastructure
Reason/Cause of conflict
Roads
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

The Char Dham (more correctly, the Chhote Char Dham) is a pilgrimage route that requires devotees to visit four temple shrines in in the Garhwal region of Uttarakhand. Located at altitudes between 3000 to 3500metres above sea level, these are called Kedarnath, Badrinath, Gangotri and Yamunotri.

Announced by the Prime Minister of India in 2016, the Char Dham Pariyojana is aimed at improving connectivity to the four temple shrine areas mentioned above. The project is being implemented by the Ministry of Road Transport and Highways (MoRTH). And involves widening of three national highways by 10 metres. These highways include Rishikesh-Mana, Rishikesh Gangotri and Tanakpur Pithoragarh, spread over a length of 889 Km. The entire project has been divided into 53 civil works. The project was scheduled to be completed in March 2022.

In February 2018, a non governmental organisation called Citizens for Green Doon filed an application before the National Green Tribunal (NGT) challenging the construction of this road citing the various negative environmental impacts it would cause. They also highlighted the fact that the cumulative impact of the 53 sub-projects had never been considered as no environmental impact assessment was conducted for them. Several trees present in forest areas have already been cut for the project without such clearances. Another application pointed out the need for responsible muck disposal and slope stabilisation.

In September 2018, the NGT ordered that since the project was divided into smaller portions whose length was less than 100 Km, there was no need for conducting environmental impact assessment. However, given the fragile nature of the region, the NGT constituted an oversight committee that would be responsible for monitoring environmental impacts of the project. This committee was tasked with ensuring the implementation of the environment management plan that would be prepared by the Ministry of Environment, Forests, and Climate Change.

This decision was challenged by the Citizens for Doon in the Supreme Court. In 2019, the Supreme Court modified the order and constituted a High Powered Committee (HPC) to “consider the cumulative and independent impact of the Char Dham Project on the entire Himalayan valleys”. The committee was also tasked with recommending measures to mitigate adverse environmental impact of the project, in consultation with experts and local communities.

Submitting its report in July 2020, the committee members unanimously acknowledged the negative impacts of this project on the environment and suggested measures to at least partially mitigate these impacts. However, the members disagreed on the width of the road, with the 13 members in favour of a two lane road with paved shoulders which would need a width of 12 metre as directed in a 2012 MoRTH circular. Five members including the Chair recommended a 5.5 metre wide road, in line with another MoRTH circular, issued in 2018. 

In September 2020, the Supreme Court accepted the recommendation of keeping the width of the road to 5.5 metre. However, the project continued to be implemented in a way that violated this order. This was followed by several different applications filed in the Supreme Court seeking directions to the MoRTH to comply with the Court's 2020 order.

One application was also filed by the Ministry of Defence seeking a modification in the Court's 2020 order. It was argued that widening of the highways was a matter of national security. As that would allow smooth mobilisation of military resources in the hill border areas, should the need arise.

In December 2021, the Supreme Court allowed the double lane with paved shoulder width for three strategic highways and directed that the remedial measures directed by the HPC be implemented. The Court also set up another oversight committee to assess the implementation of these measures. 

According to Mr. Aranya Ranjan, a resident of Khadi village in Uttarkashi district, sizeable cracks have developed in his and three of his neighbours' house, subsequent to the excavation for the highway. While they complained to the administration, the Patwari (the local revenue administrative official) came and pasted a notice on the affected houses stating they were no longer safe for habitation and should be evacuated. "Where are we supposed to go?," asks Mr. Ranjan. He pointed out that landowner’s associations and taxi associations in many towns along the highways had come together to protest the damage caused by the project. 

In a few villages where residents have received compensation, there are grievances about the different compensation rates used for calculating compensation. Inconsistencies in land values across administrative circles has meant that while some people have received market value for their land, while their immediate neighbours received much less. Some families have also discovered that they do not have rights to the land they have occupied and tended for generations.

Another group of community members who have been affected by the Char Dham project are the pastoralists of Uttarakhand. Mr. Ranjan says, "earlier, shepherds would use these routes during their annual migration to the bugyals (high altitude pastures). They had selected watering points and resting points for their sheep. Now this road is built with high concrete wall boundaries on both sides. The shepherds and their flocks have no way of accessing these ancient resting places. Rather than exhaust their animals by long forced marches, some have taken to transporting their animals by truck. But how is this viable for already poor shepherds?."

2
Fact Sheet

Demand/Contention of the Affected Community

Opposition against environmental degradation

Complaint against procedural violations

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Common and Private

Forest and Non-Forest

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Project underway despite protests

Original Project Deadline

2022

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Other Natural Resource extraction/dependence, Water bodies, Religious/Sacred/Cultural value

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

11700

Type of investment:

Cost of Project

Year of Estimation

2016

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Ministry of Road Transport and Highways, Border Roads Organisation, Ministry of Defence, Uttarakhand State Public Works Department, Defence Geo-Informatics Research Establishment

PSUs Involved in the Conflict:

National Highway and Infrastructure Development Corporation Limited (NHIDCL), Tehri Hydroelectric Development Corporation,

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Uttarakhand Jan Jagriti Sansthan, Vyapar Sabha, local taxi unions, and landlords

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Chicu Lokgariwar

Chicu is an independent consultant working on water conflicts with a focus on stakeholder negotiations.  Since 2008, she has worked on the assessment of environmental flows for several major rivers and studied natural resource-related negotiations conflicts in the Gangetic basin and North-Eastern India. She lives and works in the Uttarakhand Himalaya.

Show more work
Latest updates
East Jaintia Hills
Meghalaya

Violent protest during public hearing for cement plant expansion in Meghalaya's East Jaintia Hills

Narela
Delhi

Residents of Narela's Bajitpur Thakran oppose demolition of temples for defence institute, demand sports complex

Surguja
Chhattisgarh

Adivasis in Chhattisgarh's Hasdeo protest relentlessly against mining project in forest

Kamrup Metropolitan
Assam

Lawyer bodies protest against Assam government’s decision to relocate Gauhati High Court

Faizabad
Uttar Pradesh

Demands for Ram Temple, Babri Mosque at same site divides Ayodhya

Mumbai
Maharashtra

Supreme Court Allows Land Reclamation for Mumbai Coastal Road Project

Pune
Maharashtra

Farmers Refuse Land for Pune Outer Ring Road Project in Maharashtra

Surat
Gujarat

Slum Dwellers in Gujarat's Surat Stage Protest against Demolition, Forced Eviction

Fact sheet

Demand/Contention of the Affected Community

Opposition against environmental degradation

Complaint against procedural violations

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Project underway despite protests

Original Project Deadline

2022

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Other Natural Resource extraction/dependence, Water bodies, Religious/Sacred/Cultural value

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us