Uttar Pradesh
,
Vibhuti Khand
,
Lucknow
Published :
Jul 2017
|
Updated :
Lucknow: Delay in Possession by the Builder incensed Allottees of Parsvanath Planet
Reported by
Aashish Deep
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
542
Households affected
People affected
2009
Year started
ha.
Land area affected
542
Households affected
People Affected
2009
Year started
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Township/Real Estate
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
Sector
Infrastructure
Reason/Cause of conflict
Township/Real Estate
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
1
Summary

Parsvanath Developers launched a multi-storey housing project in Lucknow's Vibhuti Khand around 2006. The project had almost 500 flats, which were all booked. The builder promised to complete the project by 2009 but even after over 10 years the construction was still incomplete. Aggrieved allottees have been frequenting the builder's office to get the possession. Although the builder claims that most of the allottees have been given possession but allottees draw a different picture. According to the allottees, the builder has left the flats incompletely constructed quoting the soared market prices of the raw materials and have been asking the families to contribute by completing the leftover construction.
In 2013, around 250 allottees of Parsvanath Planet went on a day long hunger strike to urge the builders to complete the construction long been overdue since 2009. In 2017, the Supreme court ordered Parsvnath Planet to give possession of habitable flats in two-weeks time to its howm-buyers and provide all assured amenities, including with occupancy certificate, in two months time. The order came after 12 homebuyers petitioned in Supreme court against Parsvnath Planet.
In 2018, allottees again filed cases against the builders in the consumer disputes redressal commission. In the interim order, the National Consumer Disputes redressal commission in New Delhi on July 2019, ordered that a penalty of Rs 50,000 was imposed on Parsvnath developers for delay in responding to the court. The case is ongoing.

2
Fact Sheet

Demand/Contention of the Affected Community

No items found.

Other Demand/Contention of the Affected Community

Demanding allotment of houses

Region Classification

Urban

Type of Land

Private

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Lucknow Development Authority

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Parsvnath Builders

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Allottees of Parsvnath Planet

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Aashish Deep
Show more work
Latest updates
Karbi Anglong
Assam

Controversy erupts over Assam's 1000 MW solar power project in Karbi Anglong

Chengalpattu
Tamil Nadu

EC for Sun Pharma's expansion in Vedanthangal bird sanctuary put to abeyance

Purulia
West Bengal

Land acquisition for Turga storage project in West Bengal violates FRA

Hooghly
West Bengal

Hooghly residents in West Bengal oppose railway project over water body

Paschim Medinipur
West Bengal

Jindal Group returns land to West Bengal government, land losers demand jobs

Sundergarh
Odisha

Villagers in Odisha's Sundergarh protest over delay in R&R settlement for land acquired in 1988 for Mahanadi Coalfields

Nuapada
Odisha

Displaced people of Lower Indra Irrigation project await rehabilitation

Jajpur
Odisha

Farmers affected by Angul-Sukinda railway line in Odisha demand adequate compensation

Fact sheet

Demand/Contention of the Affected Community

No items found.

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us