Odisha
,
Kodingamali
,
Koraput
Published :
Nov 2020
|
Updated :
March 20, 2025
Tribes in Odisha's Kodingamali Hills unite, demand bauxite mining to be stopped
Reported by
Krithika A
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
People affected
2018
Year started
435
ha.
Land area affected
Households affected
People Affected
2018
Year started
435
Land area affected
Key Insights
Sector
Mining
Reason/Cause of conflict
Bauxite Mining
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Mining
Reason/Cause of conflict
Bauxite Mining
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

The Kodingamali Bauxite Mining Project was started in February 2018 by the Odisha Mining Corporation (OMC) in Koraput district. The Kodingamali mines are part of the Kodingamali Reserve Forests, comprising 12 protected forests and six reserved forest areas in the buffer zone of the mining operations. The project received the environmental clearance on 28 May 2008, for an area of 447.27 hectares.

The Stage II forest clearance was obtained on 25 September 2017, for 434.935 hectares. OMC signed a Memorandum of Understanding in 2004 with Vedanta to supply 70 per cent of the bauxite from the mines to the latter for its controversial aluminium refinery in Kalahandi district. A mining contractor, Mythri Infra, was hired by the OMC for excavation and mining. OMC had initially planned to supply bauxite to Vedanta from the Niyamgiri mines, but when that project was rejected, OMC considered bauxite supply from Kodingamali.

Tribal communities in Kodingamali village have protested against the mining operations, highlighting issues of irregularities in the forest clearance, inadequate livelihood opportunities and water and air pollution in the area from mining operations. The area falls under Schedule V of the Panchayats (Extension to Scheduled Areas) Act, or PESA. The tribespeople allege that the provisions of PESA were not followed nor was their consent taken while granting forest clearance to the project. The mining is not happening as per laws. The authorities are running the mine in an illegal manner. They should have conducted public hearings before opening the mine, but these processes were not conducted. They have established their monopoly here. We have waited for two years now, but no development has happened that was promised to us. We just want this mine to be shut and trees to be planted in its place, Akhil Chandra Jhatia, a protestor, told a local news channel.

In April 2018, five forest dwellers were arrested for allegedly torching a tipper of the OMC, following which mining was halted for some time. In August, Pradeep Kumar Bagh, president of the Kodingamali Suraksha Manch, filed a public interest litigation (PIL) at the Orissa High Court to stop the excavation and transportation of minerals. However, this was withdrawn by the petitioner with a request to file again as the court said that OMC and Vedanta should have been made parties in the PIL. In November, some villagers filed a complaint with the Odisha State Pollution Control Board on effluents being discharged into the agricultural fields from the mines. This was followed by a complaint to the District Collector.

In September 2019, residents of 24 villages, including Kodingamali, protested against Vedanta in Koraput, demanding fresh hearings with the village assembly for the mining project. The agitation ended after the district administration assured the protesters that the procedure will be started afresh.

In December the same year, the Orissa High Court ordered the secretary of the State Mines Department to look into the matter and to stop illegal mining at the Kodingamali mines in Laxmipur area of Koraput.

In February 2020, OMC proposed to enhance the production capacity from 3.0 MTPA to 6.0 MTPA. In pursuance of the EIA Clearance of the expansion, public hearings were supposed to be held which have been postponed multiple times due to resistance of local people. The affected villagers had also filed a written objection against the Public Hearing to the Ministry of Environment, Forest, and Climate Change.

Further, OMC and Mythri Infra Ltd have been accused by the workers of not providing minimum wages and other benefits as per labour norms which let to workers protesting for 83 days in front of the Collectors office. Workers also allege that while the firm had committed to hiring 70 % of the workforce from local areas, it has engaged most workers from the neighbouring state of Andhra Pradesh.

2
Fact Sheet

Demand/Contention of the Affected Community

Complaint against procedural violations

Opposition against environmental degradation

Refusal to give up land for the project

Other Demand/Contention of the Affected Community

Demand for livelihood opportunities, demand for scrapping of mining operations

Region Classification

Rural

Type of Land

Common

Forest

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Project underway despite protests

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Other Natural Resource extraction/dependence, Residential area

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

42.48

Type of investment:

Cost of Project

Year of Estimation

2016

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

PSUs Involved in the Conflict:

Odisha Mining Corporation Limited

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

N/A

Communities/Local Organisations in the Conflict:

Kodingamali Suraksha Manch

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Krithika A

Krithika A. Dinesh is a lawyer and researcher. After completing her graduation in Economics and Law from Delhi University, she went on to work on environmental justice issues for four years. She has formerly worked with the Centre for Policy Research and Namati on issues of environmental law compliance that affect communities, trying to resolve them through legal empowerment. She is currently pursuing her Masters in Environment and International Development from the University of East Anglia, England.

Show more work
Latest updates
Karbi Anglong
Assam

Controversy erupts over Assam's 1000 MW solar power project in Karbi Anglong

Chengalpattu
Tamil Nadu

EC for Sun Pharma's expansion in Vedanthangal bird sanctuary put to abeyance

Purulia
West Bengal

Land acquisition for Turga storage project in West Bengal violates FRA

Hooghly
West Bengal

Hooghly residents in West Bengal oppose railway project over water body

Paschim Medinipur
West Bengal

Jindal Group returns land to West Bengal government, land losers demand jobs

Sundergarh
Odisha

Villagers in Odisha's Sundergarh protest over delay in R&R settlement for land acquired in 1988 for Mahanadi Coalfields

Nuapada
Odisha

Displaced people of Lower Indra Irrigation project await rehabilitation

Jajpur
Odisha

Farmers affected by Angul-Sukinda railway line in Odisha demand adequate compensation

Fact sheet

Demand/Contention of the Affected Community

Complaint against procedural violations

Opposition against environmental degradation

Refusal to give up land for the project

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Project underway despite protests

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Other Natural Resource extraction/dependence, Residential area

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us