Sunrise Apartments' Allotees waiting for possession for 15 years
Reported by
Aashish Deep
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
3360
People affected
2002
Year started
4
Land area affected
Households affected
3360
People Affected
2002
Year started
4
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Township/Real Estate
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
Sector
Infrastructure
Reason/Cause of conflict
Township/Real Estate
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban
Ended
1
Summary

Sunrise Apartments project is located in SectorP, Kanpur Road near Amausi Airport. This is a composite township of flats, plots, duplex houses and a commercial establishment. The project started in 2002 and it was to be completed in 2012. But, owing to the agitation of farmers due to lower compensation for their land on which the project was being built, there was delay in providing flats to the buyers. Over 600 families have fully paid for the flats that they have been waiting for since over 15 years now. They have been continuously filing complaints about the delayed possession. After High Court's intervention in 2014, the LDA and Housing and Development Board promised to begin the work in 2014 but nothing of that sort happened. It was only later that LDA took a serious cognizance of the delay and began construction. However, the issue with the farmers hasn't been resolved, according to a report. The said land on which farmers are demanding compensation is nazul land, which according to officials farmers are not eligible for compensation on nazul land. Nazul land is the land situated beyond two miles of the Municipal Limits, which is reverted back to the State Government and has not already been appropriated by the State Government for any purpose. But the officials said in 2014 that they were working on the middle path to give farmers their dues as they depended on the land for their livelihood. In 2019, the UP government announced along with the UP Real Estate Regulatory authority (RERA) that it will waive penal interest and other dues on builder who misses deadlines to give possession to allottees. This is because the LDA failed to give possession of land to them in time. The builders however are expected to provide homes to the buyers by June 2021. As of recently, the sunrise apartments has been built and people have possession of the flats.

2
Fact Sheet

Demand/Contention of the Affected Community

No items found.

Other Demand/Contention of the Affected Community

Region Classification

Urban

Type of Land

Private

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

Yes

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Lucknow Development Authority

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Indus Projects Limited

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Allottees of Sunrise Apartments

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Aashish Deep
Show more work
Latest updates
Nagaon
Assam

Farmers in Assam resist land acquisition for solar plant, beaten by police

Surat
Gujarat

Surat farmers claim fertile land re-included in Gujarat's development plan without consent

Gadchiroli
Maharashtra

Villagers in Gadchiroli campaign to shut down Surjagarh iron ore mine

Biswanath
Assam

Encroachment, land dispute pose threat to newly designated Behali Wildlife Sanctuary in Assam

Krishnagiri
Tamil Nadu

Residents in Krishnagiri protest against takeover of land by SIPCOT

Lower Siang
Arunachal Pradesh

Tension in Arunachal's Lower Siang over Likabali-Durpai road project amid boundary disputes

Kanyakumari
Tamil Nadu

Tamil Nadu revives plan to construct Kanyakumari Port despite protests by fisherfolk

Koraput
Odisha

Bauxite mining at Mali Parbat in Koraput seeks to displace and disrupt local livelihoods

Fact sheet

Demand/Contention of the Affected Community

No items found.

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference