Tamil Nadu
Naganenthal, Valamavoor, Thiruppalaikudi, Morepannai
,
Uppur
,
Ramanathapuram
Published :
Mar 2020
|
Updated :
January 13, 2025
Madras HC stays construction of Uppur thermal plant citing defunct land laws
Reported by
Land Conflict Watch
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
People affected
2014
Year started
369
ha.
Land area affected
Households affected
People Affected
2014
Year started
369
Land area affected
Key Insights
Sector
Power
Reason/Cause of conflict
Thermal Power Plant
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Power
Reason/Cause of conflict
Thermal Power Plant
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

A super critical coal thermal power plant, with a capacity of 1,600 megawatt, was proposed in Ramanathapuram district in 2011 by the Tamil Nadu Generation and Distribution Corporation (TANGEDCO). The plant was approved by the state the same year. While TANGEDCO is the executing agency, it has contracted Bharat Heavy Electricals Limited for the Boiler, Turbine and Generators project; Larsen and Toubro for the sea water intake and outfall project; and Reliance Infrastructure to implement the remaining project activities.

The plant construction demands acquisition of agricultural and coastal land and proposes to draw sea water through an eight-kilometre pipeline, which would act as a coolant for the thermal unit.

In 2014, public consultation for the proposed project was held, in which individuals and members of various organisations, including the Coastal Action Network, an advocacy and research foundation, expressed their opposition to the construction of the power plant, citing potential damage to agricultural lands, fishing hamlets, mangrove forests and marine life in the Gulf of Mannar biosphere reserve. They say land acquisition for the project will affect the livelihoods of both farmers and fisherfolk.

The project received clearance from the Ministry of Environment, Forest and Climate Change in May 2016 and construction began in July that year. Community collectives - Anti-Uppur Thermal Power Station Struggle Committee and Anaithu Vivasayigal Paadhukappu Nala Sangam - protested to stall the construction. The Madurai bench of the Madras High Court issued a stay order on the construction of the plant, citing that land for the project was acquired using defunct land laws and not according to the Land Acquisition, Rehabilitation and Resettlement Act of 2013.

However, despite the stay order, in the beginning of 2018, a 1.25-kilometre stretch of the proposed pipeline was constructed, which led to further protests by the fishing community in June 2018.

Land Conflict Watch got in touch with a member of the Ramanathapuram district fishing community workers’ union group (a unifying body for all the 119 fishing villages in the district) and with an environmentalist from Poovulagin Nanbargal, an environmental organisation, to gather insights about the ground situation.

At present, project activities have been temporarily suspended following the stay order. TANGEDCO has appealed to the Supreme Court to consider the land acquired for the project as legal as construction has already started. The project completion date was later revised to December 2020.

As of January 2025, the project is yet to take shape despite years of planning. The plant, which was envisioned to meet growing energy demands in the state, remains stalled due to key viability and compliance reports that have not been prepared.

Local communities and environmentalists have expressed concerns about the potential environmental and social impacts of the plant, including land acquisition, pollution, and displacement. While the project’s environmental "de-shuttering" process has been initiated—a move to mitigate certain environmental risks—the broader issues of financial viability and regulatory compliance remain unresolved.

Without these critical steps, the project remains in limbo, causing uncertainty among the affected communities who are caught between the fear of displacement and the delayed execution of the project.

In June 2024, a report by DT Next stated that Tangedco has decided to revive the 1600 MV Uppur project via PPP mode. However, more details are awaited.

The delays in the Uppur Power Plant highlight the challenges of large-scale energy projects in India, where environmental concerns, regulatory bottlenecks, and community rights often clash with development goals. The situation also raises questions about the state’s preparedness to balance energy needs with sustainable development practices.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Refusal to give up land for the project

Opposition against environmental degradation

Other Demand/Contention of the Affected Community

Stalling construction of Uppur thermal power plant

Region Classification

Rural

Type of Land

Common and Private

Forest and Non-Forest

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Project underway despite protests

Original Project Deadline

2020

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Agricultural land, Non-agri rural enterprise, Other environmental services

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

12778

Type of investment:

Cost of Project

Year of Estimation

2011

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Tamil Nadu Generation and Distribution Corporation Limited, Bharat Heavy Electricals Limited

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Reliance Infrastructure, Larsen and Toubro

Did LCW Approach Corporate Parties for Comments?

No

Communities/Local Organisations in the Conflict:

Coastal Action Network; Anti-Uppur Thermal Power Station Struggle Committee; Anaithu Vivasayigal Paadhukappu Nala Sangam

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Land Conflict Watch
Show more work
Latest updates
Ukhrul, Kamjong, Tengnoupal, Chandel
Manipur

Several mining agreements in Manipur granted without villagers' consent, environmental clearances

Gir Somanath
Gujarat

Gujarat farmers oppose land acquisition for Kodinar-Somnath railway project

Karbi Anglong
Assam

Controversy erupts over Assam's 1000 MW solar power project in Karbi Anglong

Dima Hasao
Assam

Environmental Devastation and Human Fatalities: The Crisis of Illegal Coal Mining in Dima Hasao's Abandoned Mines

South Goa
Goa

In water-stressed Sancoale, locals protest Bhutani project with 700 swimming pools

Gir Somanath
Gujarat

Gujarat puts solar power project near Gir sanctuary on hold amid protest

Dimapur
Nagaland

Global Naga Forum calls for relocation of Assam Rifles camps from urban areas

Dimapur
Nagaland

DNSU demands relocation of sub-centre in GMC Midland

Fact sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Refusal to give up land for the project

Opposition against environmental degradation

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Project underway despite protests

Original Project Deadline

2020

Whether the Project has been Delayed

Yes

Significance of Land to Land Owners/Users

Agricultural land, Non-agri rural enterprise, Other environmental services

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us