Rajasthan
,
Ninder
,
Jaipur
Published :
Feb 2017
|
Updated :
Farmers Oppose Land Acquisition by Jaipur Development Authority at Nindar
Reported by
Manish Tiwari
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
1920
People affected
2010
Year started
287
ha.
Land area affected
Households affected
1920
People Affected
2010
Year started
287
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Township/Real Estate
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Infrastructure
Reason/Cause of conflict
Township/Real Estate
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

The Jaipur Development Authority's biggest housing scheme at Ninder village seems to have fallen flat as the government authorities are facing problems in acquiring land. The proposed scheme will have 10,000 houses. In December 2010, Jaipur Development Authority (JDA) had proposed this scheme on 1,100 bighas of land in Ninder village on Sikar Road. Ninder village is just 20 km away from Ajmeri Gate area in Jaipur. As much as 900 bighas needs to be acquired from the private land owners. The government has allotted around 200 bighas for the scheme. JDA is finding it difficult to acquire land because many land owners have denied to give away their land. The land owners have intensified their protest and carried out a torch march. In October 2017, about 50 farmers Launched 'Zameen Samadhi Satyagraha' demanding compensation as per the Land Acquisition Act, 2013. A similar protest was held again in February 2020 demanding fair compensation. In December 2020, JDA officials started a fresh round of talks with farmers on matters pertaining to land acquisition.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Complaint against procedural violations

Other Demand/Contention of the Affected Community

Demand to pay token lease money only for developed land received as compensation in lieu of acquired land

Region Classification

Rural

Type of Land

Private

N/A

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

800

Type of investment:

Cost of Project

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

Jaipur Development Authority

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

ninder bachao samiti

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Manish Tiwari
Show more work
Latest updates
Surendranagar
Gujarat

Protests against solar power plant in Dhrangadhra’s Moti Malvan village in Gujarat

Tiruvannamalai
Tamil Nadu

Farmers protest new SIPCOT industrial complex project in Tamil Nadu's Thiruvannamalai

Visakhapatnam
Andhra Pradesh

Farmers demand compensation for land diverted for thermal power plant in Vishakhapatnam

Nainital
Uttarakhand

6 killed in Haldwani amid protest over demolition of mosque and madrasa

Pune
Maharashtra

Pune residents protest felling of trees for transit corridor, fear groundwater contamination

North Delhi
Delhi

DDA razes down encroachments near Azadpur Mandi in Delhi, 250 families rendered homeless

North West Delhi
Delhi

Residents of Delhi's Shakur Basti continue to live in fear of demolition

Jalgaon
Maharashtra

Farmers in Maharashtra's Jalgaon allege 1100 acres fraudulently acquired by solar power companies

Fact sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Complaint against procedural violations

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Conflicts Map
Conflict Database
About Us