Gujarat
,
Surat
,
Surat
Published :
Jul 2024
|
Updated :
February 21, 2025
Farmers protest against 765 KV power transmission line in Surat
Reported by
Suchak Patel
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
People affected
Year started
ha.
Land area affected
Households affected
People Affected
Year started
Land area affected
Key Insights
Sector
Power
Reason/Cause of conflict
Transmission Lines
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban and Rural
Ended
Sector
Power
Reason/Cause of conflict
Transmission Lines
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Urban and Rural
Ended
1
Summary

In Surat, farmers have been vehemently protesting against a new 765 KV power transmission line being laid by the Power Grid Corporation of India Limited. Stating that they have already lost fertile agricultural land to highways, expressways, and bullet trains, the farmers are determined to not give their land for the power line project.

The new power line is being laid from Khavda in Kutch to Vansi Borsi in Navsari via Surat. In May, Power Corporation officials started survey operations in Mandvi and Palsana talukas of Surat district without informing the farmers, kickstarting the protests. In June, farmers from Mangarol, Mandvi, Kamrej, Bardoli and Palsana talukas of Surat district protested outside the Collector's office, raising the slogan 'jan denge zamini nahi' (we will give our lives but not land).

Parimal Patel, President of the Surat District Farmers' Association, stated that the power line is set to cut through fertile farmland, exacerbating past land losses due to other infrastructure projects. According to a report by the Navgujarat Samachar, the new power line involves erecting towers on 85-foot by 85-foot plots. Farmers are demanding that the power lines be laid underground in urban areas or along the Gujarat coast.

The process of acquiring land for power lines differs significantly from that for highways. During the expressway construction, farmers received compensation for their land. However, the Telegraph Act of 1885, still used for power line projects, provide very less compensation or benefits to farmers. This outdated Act was initially meant for telephone poles, which had minimal impact on agriculture.

Jayesh Patel, President of Gujarat Khedut Samaj, expressed his concerns, saying, "We don't understand how this government is erecting electricity towers by misinterpreting the Telegraph Act meant for communication." He also pointed out that the Electricity Act of 2003 has been misinterpreted, leading to the oppression of farmers and the potential ruin of fertile land.

Meanwhile, farmers alleged that company staff forcibly entered their fields without permission and damaged their crops. While the Power Grid Corporation is said to have issued notices to farmers, the latter claims that the company has not given any information about the project and how many farmers will be affected by this power line.

In January 2025, the dispute flared up again as farmers protesting against the commencement of work by Power Grid officials clashed with the police. According to a report by the Bhaskar, the police had to forcefully take the farmers to the police station.

The farmers insisted that compensation be determined strictly as per the criteria set by the Collector, however, the company officials refused to conduct a new calculation without the written order of the Collector. Efforts by Surat District Farmers' Association President Parimal Patel to arrange a discussion with the Collector failed, as the officials remained adamant about proceeding with the work, further aggravating the situation. The company had tried to start the work on 16 December 2024 too but the work was halted after strong opposition from farmers.

2
Fact Sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

Demand to retain/protect access to common land/resources

Complaint against procedural violations

Other Demand/Contention of the Affected Community

Farmers are demanding that the power lines be laid underground in urban areas or along the Gujarat coast.

Region Classification

Urban and Rural

Type of Land

Private

Non-Forest (Other than Grazing Land)

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Agricultural land

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Suchak Patel
Suchak is an independent researcher.
Show more work
Latest updates
Karbi Anglong
Assam

Controversy erupts over Assam's 1000 MW solar power project in Karbi Anglong

Chengalpattu
Tamil Nadu

EC for Sun Pharma's expansion in Vedanthangal bird sanctuary put to abeyance

Purulia
West Bengal

Land acquisition for Turga storage project in West Bengal violates FRA

Hooghly
West Bengal

Hooghly residents in West Bengal oppose railway project over water body

Paschim Medinipur
West Bengal

Jindal Group returns land to West Bengal government, land losers demand jobs

Sundergarh
Odisha

Villagers in Odisha's Sundergarh protest over delay in R&R settlement for land acquired in 1988 for Mahanadi Coalfields

Nuapada
Odisha

Displaced people of Lower Indra Irrigation project await rehabilitation

Jajpur
Odisha

Farmers affected by Angul-Sukinda railway line in Odisha demand adequate compensation

Fact sheet

Demand/Contention of the Affected Community

Refusal to give up land for the project

Demand to retain/protect access to common land/resources

Complaint against procedural violations

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Agricultural land

Whether the project was stalled due to land conflict

Source/Reference