Uttar Pradesh
,
Bara
,
Allahabad
Published :
Sep 2016
|
Updated :
Farmers oppose 3300 MW Bara Power Plant in Uttar Pradesh's Prayagraj district
Reported by
Rama Shanker Singh
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
Households affected
9600
People affected
2009
Year started
645
Land area affected
Households affected
9600
People Affected
2009
Year started
645
Land area affected
Key Insights
Sector
Power
Reason/Cause of conflict
Thermal Power Plant
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Power
Reason/Cause of conflict
Thermal Power Plant
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

Bara Thermal Power Project was conceived in 2009 by the Jaypee Group of Industries. The project is situated at Bara in Prayagraj district of Uttar Pradesh, India. The first phase of 1980 MW commenced operations in 2014. The second phase of a 3300 MW thermal power plant is under construction. However, the farmers, whose land was acquired for the project are unhappy with the compensation given for their land. They are demanding better compensation for their agricultural land. The farmers also claim the company had also made some promises with regards to providing job to one person of every family. The promises have not been fulfilled. In 2011, protests against the company turned violent. Police vehicles arrived at the protest scene. One farmer was killed in the police firing. The UP Government denies this. Protesters also damaged computers, vehicles, canteen and other facilities belonging to the company. The main contention for the protests were fulfilling their demand including providing employment for the affected at the project site. In 2016, it was reported that the farmers have given up on their demands for higher compensation. However, they launched a movement against the excess extraction of water from the Yamuna. In November 2019 Resurgent Power Ventures Pte. Limited (Resurgent Power) announced closing the deal for acquiring 75 per cent stake in Jaiprakash Associates Ltds Prayagraj Power. The power plant is in advanced stage of construction and the protests have reduced in intensity, Vindhyan Ecology and Natural History Foundation, a local non-profit, informed Land Conflict Watch in April 2020.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Complaint against procedural violations

Opposition against environmental degradation

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Private

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

12000

Type of investment:

Cost of Project

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

UTTAR PRADESH POWER CORPORATION

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Jaypee Group, Jaiprakash Power Ventures Ltd

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

KISAN KALYAN SANGHRSH SAMITI

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Rama Shanker Singh


Show more work
Latest updates
East Jaintia Hills
Meghalaya

Violent protest during public hearing for cement plant expansion in Meghalaya's East Jaintia Hills

Narela
Delhi

Residents of Narela's Bajitpur Thakran oppose demolition of temples for defence institute, demand sports complex

Surguja
Chhattisgarh

Adivasis in Chhattisgarh's Hasdeo protest relentlessly against mining project in forest

Kamrup Metropolitan
Assam

Lawyer bodies protest against Assam government’s decision to relocate Gauhati High Court

Faizabad
Uttar Pradesh

Demands for Ram Temple, Babri Mosque at same site divides Ayodhya

Mumbai
Maharashtra

Supreme Court Allows Land Reclamation for Mumbai Coastal Road Project

Pune
Maharashtra

Farmers Refuse Land for Pune Outer Ring Road Project in Maharashtra

Surat
Gujarat

Slum Dwellers in Gujarat's Surat Stage Protest against Demolition, Forced Eviction

Fact sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Complaint against procedural violations

Opposition against environmental degradation

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference