Government issues land acquisition notice amid protests over the Amravati Metro rail project
Reported by
Rahul Maganti
Legal Review by
Anmol Gupta
Edited by
Anupa Kujur
77
Households affected
370
People affected
2016
Year started
30
ha.
Land area affected
77
Households affected
370
People Affected
2016
Year started
30
Land area affected
Key Insights
Sector
Infrastructure
Reason/Cause of conflict
Railways
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
Sector
Infrastructure
Reason/Cause of conflict
Railways
Conflict Status
Ongoing
Ended
Legal Status
Region Classification
Rural
Ended
1
Summary

In 2016, the government of Andhra Pradesh proposed the Amravati metro rail project. The metro project would need 31 hectares of land which would include government land of 1.5 hectares and private land of 29.44 hectares. At least 77 families are likely to be affected by the project. The cost of acquisition is estimated to be 750 crores and resettlement and rehabilitation cost is expected at Rs. 46.73 crore.

However, the Farmers of Nidamanuru and building owners at Karl Marx Road (Eluru Road) have opposed the land acquisition. Farmers say that they don’t want to lose their lands for the Metro Rail Project. The residents also question the need for the project. They are unhappy because the government compensation will offer them only one-fourth of the market rate for their land.
The villagers from Poranki, Kanuru, Bandar Road and Eluru Road requested officials not to acquire land in their villages during the gramsabha meeting. Nonetheless, the government went ahead with the acquisition.

However, with the change in the government in 2019, the project has been redesigned to bring down the cost. In a meeting with officials in September 2019, Chief Minister YS Reddy suggested to take over the land on lease. Finalising on this, the government has released Rs 187.40 crore of lease amount to the farmers of Amravati.

2
Fact Sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Refusal to give up land for the project

Other Demand/Contention of the Affected Community

Region Classification

Rural

Type of Land

Common and Private

Non-Forest (Other than Grazing Land)

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

7000

Type of investment:

Investment Expected

Year of Estimation

2016

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

4
Additional Information

Government Departments Involved in the Conflict:

PSUs Involved in the Conflict:

Amravati Metro Rail Corporation Ltd

Did LCW Approach Government Authorities for Comments?

No

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

No

Communities/Local Organisations in the Conflict:

Local residents, Farmers

5
Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Legal Supporting Documents

JOIN
THE LCW COMMUNITY
Exclusive monthly policy briefs, stories from the ground, Quarterly Analytics report, Curated Expert talks, merchandise and much more.


Support our work.
Sign Up Today
Author
Reported by
Rahul Maganti


Show more work
Latest updates
Surendranagar
Gujarat

Protests against solar power plant in Dhrangadhra’s Moti Malvan village in Gujarat

Tiruvannamalai
Tamil Nadu

Farmers protest new SIPCOT industrial complex project in Tamil Nadu's Thiruvannamalai

Visakhapatnam
Andhra Pradesh

Farmers demand compensation for land diverted for thermal power plant in Vishakhapatnam

Nainital
Uttarakhand

6 killed in Haldwani amid protest over demolition of mosque and madrasa

Pune
Maharashtra

Pune residents protest felling of trees for transit corridor, fear groundwater contamination

North Delhi
Delhi

DDA razes down encroachments near Azadpur Mandi in Delhi, 250 families rendered homeless

North West Delhi
Delhi

Residents of Delhi's Shakur Basti continue to live in fear of demolition

Jalgaon
Maharashtra

Farmers in Maharashtra's Jalgaon allege 1100 acres fraudulently acquired by solar power companies

Fact sheet

Demand/Contention of the Affected Community

Demand for more compensation than promised

Refusal to give up land for the project

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Whether the project was stalled due to land conflict

Source/Reference