Lawyers protest against Assam government’s decision to shift the Gauhati High Court to the outskirts of Guwahati

Reported by

East Street Journal Asia

Legal Review by

Priyansha Chouhan, Anmol Gupta

Edited by

Radhika Chatterjee

Updated by

Published on

August 2, 2023

August 3, 2023

Edited on

August 2, 2023

State

Assam

Sector

Infrastructure

People Affected by Conflict

Households Affected by Conflict

Land Area Affected (in Hectares)

25

ha

Starting Year

2023

Location of Conflict

Guwahati

Kamrup Metropolitan

Reason or Cause of Conflict

Other Kind of Infrastructure

Proposed shifting of the Gauhati high court & other courts from its present location to the outskirts of Guwahati

Land Conflict Summary

On June 27, 2023, lawyers of the Gauhati High Court Bar Association (GHCBA) staged sit-in protests opposing the proposed plan of relocating the Gauhati High Court to the Rangmahal area in the Kamrup (Rural) district of Assam.

Previously known as the High Court of Assam, Gauhati High Court was established in 1948 and the old court building was set up in 1960.

The Government plans to construct a judicial city in Assam's Amingaon where the court will be shifted to. Located in Kamrup (rural) district, the proposed location lies on the northern bank of river Bhramaputra. Amingaon city is almost 30 km away from the present courthouse.

The Gauhati high court bar association (GHCBA) submitted a memorandum to the President of India, the Chief Justice of India, the Union Law Minister, the Governor and the Chief Minister of Assam, expressing their dissent on the Government's decision to shift the present High Court.

The lawyers assert that the shifting of the court complex to a remote location would have a negative impact on their productivity as they will have to spend a longer time on commute.

While addressing the media, one of the protesting lawyers said, "There was no demand from the lawyers or the public at large that we've got difficulty in the present set-up of courts. The justification given by the government for the expansion of the courts citing that there isn't sufficient space for the people here is not true. We are suspecting that the decision may not be in the public interest but for personal gain. We believe there are vested interests involved here_._"

Chief Minister Himanta Biswa Sarma announced the release of a draft of the relocation plan on April 14, 2023. A high-level committee was formed on May 23, 2023, to examine the proposed site measuring 240 bighas, out of which 100 bighas were meant to be entitled to the Gauhati High Court, other judicial courts of the Kamrup area, and residential accommodation for judges and staff. 

GHCBA's representation stated, "The place where the proposed judicial city is to come up is yet to have any kind of infrastructure, and at present, it can be reached from Guwahati by traveling over the Saraighat Bridge, which takes about 30 km of travel, or by Ferry Service. However, a new bridge is being constructed over the river Brahmaputra by a Company which has the dubious distinction of its under-construction bridge over river Ganga collapsing like a pack of cards."

Fact Sheet

Demand/Contention of the Affected Community

Demand to cancel the project

Demand to retain/protect access to common land/resources

Other Demand/Contention of the Affected Community

To allocate space in and around the present high court location for expansion of the Judicial infrastructure

Region Classification

Urban

Type of Land

Type of Common Land

Non-Forest (Other than Grazing Land)

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Details of sources (names of accused, names and numbers of any lawyers, names of any police officers contacted)

Status of Project

Original Project Deadline

Whether the Project has been Delayed

Significance of Land to Land Owners/Users

Government or community-regulated urban commons

Whether the project was stalled due to land conflict

Source/Reference

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

Legal Data

Categories of Legislations Involved in the Conflict

Legislations/Policies Involved

  1. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  2. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  3. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  4. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  5. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  6. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  7. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

Whether claims/objections were made as per procedure in the relevant statute

What was the claim(s)/objection(s) raised by the community?

What was the Decision of the Concerned Government Department?

Legal Processes and Loopholes Enabling the Conflict:

Non-consultation with stakeholders

Legal Status:

Out of Court

Status of Case In Court

Whether any adjudicatory body was approached

No

Name of the adjudicatory body

Name(s) of the Court(s)

Case Number

Main Reasoning/Decision of court

Major Human Rights Violations Related to the Conflict:

No items found.

Whether criminal law was used against protestors:

No

Reported Details of the Violation:

Date of Violation

Location of Violation

Additional Information

Nature of Protest

Protests/marches

Complaints/petitions/letters/memorandums to officials

Campaigns (grassroots organisations/press releases/media)

Government Departments Involved in the Conflict:

Chief Secretary of Assam; Legal Remembrancer (LR) and Secretary Judicial Department; Kamrup Deputy Commissioner; Special Secretary of Public Works Department (building and national highways)

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Information on the use of criminal law

What was the action taken by the police?

How many people did the police detain or arrest?

What is the current status of the detained/accused persons?

Did the person face any violence while in police custody?

If any arrests took place, were the accused persons produced before a judge within 24 hours of the arrest?

If the accused was not produced before a magistrate within 24 hours, or not produced at all, what were the reasons?

Legislation under which the accused was charged

Was the accused person informed of their right to legal representation? Did the accused person have access to legal aid?

In cases where the accused person approached the court for bail, was bail granted?

Why was bail granted or rejected? If granted, what were the bail conditions and quantum of bail?

Were there any other notable irregularities that took place, or other significant details?

Resources

Resources Related to Conflict

  • News Articles Related to the Conflict:
  • Documents Related to the Conflict:
  • Links Related to the Conflict:

Images

Image Credit:  

Image Credit:  

Video

On June 27, 2023, lawyers of the Gauhati High Court Bar Association (GHCBA) staged sit-in protests opposing the proposed plan of relocating the Gauhati High Court to the Rangmahal area in the Kamrup (Rural) district of Assam.

Previously known as the High Court of Assam, Gauhati High Court was established in 1948 and the old court building was set up in 1960.

The Government plans to construct a judicial city in Assam's Amingaon where the court will be shifted to. Located in Kamrup (rural) district, the proposed location lies on the northern bank of river Bhramaputra. Amingaon city is almost 30 km away from the present courthouse.

The Gauhati high court bar association (GHCBA) submitted a memorandum to the President of India, the Chief Justice of India, the Union Law Minister, the Governor and the Chief Minister of Assam, expressing their dissent on the Government's decision to shift the present High Court.

The lawyers assert that the shifting of the court complex to a remote location would have a negative impact on their productivity as they will have to spend a longer time on commute.

While addressing the media, one of the protesting lawyers said, "There was no demand from the lawyers or the public at large that we've got difficulty in the present set-up of courts. The justification given by the government for the expansion of the courts citing that there isn't sufficient space for the people here is not true. We are suspecting that the decision may not be in the public interest but for personal gain. We believe there are vested interests involved here_._"

Chief Minister Himanta Biswa Sarma announced the release of a draft of the relocation plan on April 14, 2023. A high-level committee was formed on May 23, 2023, to examine the proposed site measuring 240 bighas, out of which 100 bighas were meant to be entitled to the Gauhati High Court, other judicial courts of the Kamrup area, and residential accommodation for judges and staff. 

GHCBA's representation stated, "The place where the proposed judicial city is to come up is yet to have any kind of infrastructure, and at present, it can be reached from Guwahati by traveling over the Saraighat Bridge, which takes about 30 km of travel, or by Ferry Service. However, a new bridge is being constructed over the river Brahmaputra by a Company which has the dubious distinction of its under-construction bridge over river Ganga collapsing like a pack of cards."

Demand/Contention of the Affected Community

Demand to cancel the project

Demand to retain/protect access to common land/resources

Other Demand/Contention of the Affected Community

To allocate space in and around the present high court location for expansion of the Judicial infrastructure

Region Classification

Urban

Type of Land

Type of Common Land

Non-Forest (Other than Grazing Land)

Total investment involved (in Crores):

Type of investment:

Year of Estimation

Page Number In Investment Document:

Has the Conflict Ended?

No

When did it end?

Why did the conflict end?

Categories of Legislations Involved in the Conflict

Legislations/Policies Involved

  1. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  2. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  3. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  4. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  5. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  6. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

  7. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

Whether claims/objections were made as per procedure in the relevant statute

What was the claim(s)/objection(s) raised by the community?

What was the Decision of the Concerned Government Department?

Legal Processes and Loopholes Enabling the Conflict:

Non-consultation with stakeholders

Legal Status:

Out of Court

Status of Case In Court

Whether any adjudicatory body was approached

No

Name of the adjudicatory body

Name(s) of the Court(s)

Case Number

Main Reasoning/Decision of court

Major Human Rights Violations Related to the Conflict:

No items found.

Whether criminal law was used against protestors:

No

Reported Details of the Violation:

Date of Violation

Location of Violation

Nature of Protest

Protests/marches

Complaints/petitions/letters/memorandums to officials

Campaigns (grassroots organisations/press releases/media)

Government Departments Involved in the Conflict:

Chief Secretary of Assam; Legal Remembrancer (LR) and Secretary Judicial Department; Kamrup Deputy Commissioner; Special Secretary of Public Works Department (building and national highways)

PSUs Involved in the Conflict:

Did LCW Approach Government Authorities for Comments?

LCW has called and emailed the Office of the Commissioner & Special Secretary, Public Works (Building & NH) Department. This section will be updated when we receive a response from them.

Name, Designation and Comment of the Government Authorities Approached

Corporate Parties Involved in the Conflict:

Did LCW Approach Corporate Parties for Comments?

Communities/Local Organisations in the Conflict:

Resources Related to Conflict

  • News Articles Related to the Conflict:
  • Documents Related to the Conflict:
  • Links Related to the Conflict:

Image Credit:  